Licensing Procedure for investment projects in PV Parks
Important Note: The following procedure concerns PV Parks over 500kW
Disclaimer: Whilst every care has been taken to assure that the information contained in this leaflet is accurate, Ιnvest in Greece Agency does not in any way assume liability for any imprecise or erroneous statement contained herein. This publication is not intended to impart legal advice; readers are advised to seek independent legal advice prior to acting on any statements contained herein.
1st STAGE
- ELECTRICITY PRODUCTION LICENSE
The Electricity production License is issued for 25 years, plus 25 years extension.
- DETERMINATION OF THE CONNECTION TERMS TO THE SYSTEM OR THE NETWORK (OFFER)
The offer of the Operator is valid for 2 years that can be extended by the Operator.
- INTERVENTION OR CONCESSION APPROVAL
The decision for the approval is incorporated to the Approval of Environmental Terms.
- ENVIRONMENTAL TERMS APPROVAL
- CONTRACT FOR THE CONNECTION WITH THE SYSTEM OR THE GRID
2nd STAGE
- INSTALLATION LICENSE
The installation license is valid for 2 years plus 2 years extension if 50% of the project is completed.
- POWER PURCHASE AGREEMENT (P.P.A.)
The contract is valid for 20 years.
3rd STAGE
- OPERATION LICENSE
Licensing Procedure for investment projects in Wind Parks
Important Note: The following procedure concerns Wind Parks over 50kW
Disclaimer: Whilst every care has been taken to assure that the information contained in this leaflet is accurate, Ιnvest in Greece Agency does not in any way assume liability for any imprecise or erroneousstatement contained herein.
This publication is not intended to impart legal advice; readers are advised to seek independent legal advice prior to acting on any statements contained herein.
1st STAGE
- ELECTRICITY PRODUCTION LICENSE
The Electricity production License is issued for 25 years, plus 25 years extension.
- DETERMINATION OF THE CONNECTION TERMS TO THE SYSTEM OR THE NETWORK (OFFER)
The offer of the Operator is valid for 2 years that can be extended by the Operator.
- INTERVENTION OR CONCESSION APPROVAL
The decision for the approval is incorporated to the Approval of Environmental Terms.
- ENVIRONMENTAL TERMS APPROVAL
- CONTRACT FOR THE CONNECTION WITH THE SYSTEM OR THE GRID
2nd STAGE
- INSTALLATION LICENSE
The installation license is valid for 2 years plus 2 years extension if 50% of the project is completed.
- POWER PURCHASE AGREEMENT (P.P.A.)
The contract is valid for 20 years.
3rd STAGE
- OPERATION LICENSE
The operation license is valid for 20 years, plus 20 years extension.